Analisis Perhitungan Quantity Take Off Jembatan Rangka Baja Menggunakan Metode (BIM) dengan Autodesk Revit(Studi Kasus: Perencanaan Jembatan Ruas Selat Baru - Deluk)

Authors

  • Azmi Maulana Politeknik Negeri Bengkalis Author
  • Dedi Enda Politeknik Negeri Bengkalis Author

DOI:

https://doi.org/10.62710/s9h6qs77

Keywords:

Building Information Modeling; Quantity Take Off; Bridge Construction; Accuracy Analysis

Abstract

The construction industry is increasingly adopting Building Information Modeling (BIM) to support Quantity Take Off (QTO), as conventional methods based on two-dimensional drawings, which are still widely used in Indonesia, are prone to measurement errors, inconsistent results, and time inefficiency. This study aimed to develop a three-dimensional BIM model of a steel truss bridge using a case study of the Selat Baru–Deluk Bridge with Autodesk Revit and compare the calculated concrete and reinforcement volumes with manual calculations. The model was developed by converting two-dimensional Detail Engineering Design (DED) drawings into a three-dimensional model. Volume calculations were automatically generated using the Schedule/Quantities feature in Autodesk Revit, while the conventional method used simple geometric formulas. The results showed that the average difference between the two methods was only 0.107% for concrete and 0.463% for reinforcement. The Root Mean Square Error (RMSE) values were 0.511% for concrete and 1.402% for reinforcement. These findings indicate that BIM-based quantity estimation using Autodesk Revit provides higher accuracy, efficiency, and precision compared to conventional methods in bridge QTO calculations.

Downloads

Download data is not yet available.

References

Azhar, S. (2011). Building information modeling (BIM): Trends, benefits, risks, and challenges for the AEC industry. Leadership and Management in Engineering, 11(3), 241–252. https://doi.org/10.1061/(ASCE)LM.1943-5630.0000127

Eastman, C., Teicholz, P., Sacks, R., & Liston, K. (2011). BIM Handbook: A Guide to Building Information Modeling for Owners, Managers, Designers, Engineers and Contractors (2nd ed.). John Wiley & Sons

Farizah, D. (2024). Analisis Perhitungan Quantity Take Off Menggunakan Metode BIM (Revit) Beton Bertulang

Kementerian PUPR. (2018). Pedoman Penerapan Building Information Modeling (BIM) pada Bangunan Gedung Negara.

Nafiyah, R., & Martina, N. (2022). Analisis Quantity Takeoff Pada Pekerjaan Struktur Bawah Jembatan. Construction and Material Journal, 4(2), 91-100.

Pratama, A. F., & Witjaksana, B. (2022). Implementasi Autodesk Revit Untuk Quantiiy Take Off Pada Pekerjaan Struktur Jembatan. Jurnal Kacapuri: Jurnal Keilmuan Teknik Sipil, 5(1), 408-416.

Sacks, R. and Barak, R. (2010). (n.d.). Teaching Building Information Modeling as an Integral Part of Freshman Year Civil Engineering Education. https://www.scirp.org/reference/referencespapers?referenceid=2387492

Sadad, I., Jaya, F. H., & Januar, I. W. (1960). Implementasi BIM Take Off Quantity Material Struktur Abutment Jembatan Terhadap Volume Rencana. Teknika Sains: Jurnal Ilmu Teknik, 7 (2), 91–97.

Saputra, H., Pratama, R., Tita, E. E., & Yusa, M. (2024). Comparative Analysis of Quantity Take-Off Material Between Conventional Method & BIM Nemetschek Allplan Method on Bridge. Architecture, 12(4), 2622-2633.

Stefanus, S., & Lutfiansyah, Y. (2025). Analisis Perbandingan Perhitungan Quantity Take-Off Metode Konvensional dengan Perhitungan Berbasis BIM Pada Pekerjaan Struktur Beton Jembatan: Studi kasus: Proyek Jalan Tol Trans Sumatera Ruas Rengat-Pekanbaru. Jurnal Teknik Sipil, 21(2), 249-258.

Succar, B. (2009). Building information modelling framework: A research and delivery foundation for industry stakeholders. Automation in Construction, 18(3), 357–375.

Tigauw, F. M., Aprilianto, F., & Santoso, H. T. (2023). Analisa Perhitungan Quantity Material Take-Off (QMTO) Struktur Bawah Jembatan Tipe Skew dengan Menggunakan BIM Autodesk Revit. Jurnal Inovasi Konstruksi, 2(2), 58-65.